Scray Hill Road Project
Contractor has finished storm sewer installation on Scray Hill Road and is working on the grading for the roadway on the top of the hill down to Limestone Trail. Curb and gutter is scheduled to begin on September 10th.  During the curb and gutter installation, you will not be able to access your driveway once the curb and gutter is poured for about 5-7 days. The contractor will notify you about 24 hours prior to this occurring. You will have to park on a side street or Scray Hill Road at night. Once the concrete has cured sufficiently, the contractor will ramp gravel over the curb so you can access your driveway.  When the sidewalk and driveway apron are poured you will need to park on the street again. We will notify you again when this will occur.

Estimated completion is mid to late October. The project is weather dependent.

Bower Creek Road and Red Hawk Landing Subdivision
Curb and gutter will be starting this week in phase 2. Once they are done with the curb and gutter, the contractor will move to the sidewalk and driveways on Bower Creek.  During the driveway concrete work you will not be able to access your driveway similar to when the curb and gutter was poured.  The contractor will notify you about 24 hours prior to this occurring.

Bower Creek just north of CTH G, WPS is installing gas and electric this week.  Contractor continues to place fill at the creek crossing for the widened road.

Estimated completion is mid to late October. The project is weather dependent.

Pine Grove Road
Pine Grove Road is open to traffic

Creamery Road, Kaftan Way, Easts River Drive and Ledgecrest Ln   
The granite seal has been placed. Excess material will be swept this week.